Highlights:

On site crushing and screening

Project Overview

Geomembrane lining (11,000 sf) and rockfill ballast repair for timber crib/shotcrete dam. Process and place approximately 6,000 CY of filter sand, rockfill, and riprap. Repair of existing shotcrete dam face (11,000 sf). Install new intake structure and pipe. Placement of approximately 120 CY of structural and backfill concrete to stop leaks in the dam foundation. Dam located at 10,500 ft. elevation.

Technical Details:

Type of Dam:  Timber crib/shotcrete